Work to
restore PATH service to Downtown Manhattan
is ahead of schedule with resumption of
train service to a new temporary passenger
terminal at the World Trade Center site
expected in November.
The PATH
Terminal at the World Trade Center served
some 67,000 passengers per day when it was
destroyed in the September 11, 2001
terrorist attacks. With resumption of PATH
service to Downtown Manhattan as its top
priority, the Port Authority forged a unique
partnership that allowed contractors to
order materials and mobilize for
construction even as engineers were
completing design work. This collaborative
approach, coupled with non-traditional
sequencing of tunnel work and track
installation, promises train service to the
World Trade Center site will begin fully a
month ahead of the original end of December
2003 goal.
The collapse of the World Trade Center
caused severe flooding of the PATH tunnels
under the Hudson River between the World
Trade Center and Jersey City damaging track
systems, cables, duct banks and concrete,
electrical components including switch and
signal equipment, and track ballast.
The work to
restore the two-mile long tunnels began in
March 2002. Only the 16 foot wide cast iron
tunnel ring liners were left once all water
damaged equipment had been demolished and
debris removed-the very rings that became
famous a century ago as the "Hudson
Tubes." Remarkably, these cast iron
rings were sound, having sustained little
damage. However, corroded and leaking
ringbolts had to be repaired. The ring
liners were power-washed, and concrete
invert, track bed
and track support structure restored.
Finally, duct banks, cables for high
voltage, traction power, signals and
communications installed, not to mention the
lighting, drainage, fire protection,
in-tunnel communication and signal systems
had to be replaced. Over 11,000 feet of new
track, 5600 feet in each tunnel, along with
third rail, had to be installed.
Every
opportunity was seized to accelerate
progress even while upgrading materials and
construction techniques to state of the art
industry standards. Traditional construction
methods would call for the installation of
conduits and duct banks after the
installation of track. This order was
reversed so that concrete delivery trucks
could use the tunnel floor and feed material
to the worksite. First fiber reinforced
epoxy conduit replaced the old clay ducts
and steel reinforced concrete duct banks
succeeded the old asbestos lined duct banks.
"This
was a special challenge in tunnels where
clearances were very tight--as small as two
inches beyond the dynamic envelope of a PATH
train," says Jim Palmer, a Program
Management Consultant. "We had the real
fear that as we rebuilt the tunnels, trains
might hit the walls," he adds. The
solution was building a "brush
car" template to accurately measure
clearances.
Another technological advance is the use of
continuous-welded-rail in place of the
standard 39-foot lengths of rail that give
that familiar clickety-clack sound to most
railroads. Some 560 tons of 115lb/yard rail
in 39 foot lengths and 150 tons of
100lb/yard rail were delivered to the World
Trade Center Bathtub, and welded using an
electric fusion process into 1440 foot
continuous lengths.
"Using a
big powerwheel, the welded rails were pushed
and dragged like shining strands of linguini
into the tunnels," says Tom Groark,
Manager, Construction Management Division.
Once in
place, the rail sections were bolted
together and field welded forming
continuous-welded-rails. According to Ernie
Perry, Assistant Resident Engineer-Track,
the 37,644 linear feet of rail sections
required over a thousand individual welds in
the field using a process similar to casting
molten metal.
Continuous-welded-rail does a lot more than
get rid of the old clickety-clack. It is
stronger and more dependable and gives a
smoother ride. In addition, with the
introduction of the direct fixation fastener
system to anchor the rails instead of using
customary wooden railroad ties and gravel
ballast for securing rail to the track bed,
trains will sway less in the century-old
tunnels.*
Passengers are sure to notice a smoother,
quieter and more comfortable ride.
After the attacks, all that remained of the
original PATH World Trade Center Terminal
was part of a platform and an escalator
bank. In order to restore train service to
the site as quickly as possible, a temporary
terminal is being built at the same location
as the destroyed facility. This enables
engineers to utilize previous alignments and
minimize additional excavation and
foundation work. However, a new traction
power substation located adjacent to the
former South Tower footprint has been
designed to support future construction of
floor levels up to the street level. This
"over build" scenario is intended
to eliminate the need to build future
support columns through the substation in
the future development of the World Trade
Center site.
The track and
platform configuration of the temporary
station will mimic the former station. The
terminal will have a mezzanine above the
platforms where turnstiles will be located,
with stairs and elevators connecting the two
levels. From the mezzanine, passengers will
follow previous pedestrian pathways to
escalators, elevators and stairs up to
street level on Church Street.
The temporary station was designed to
facilitate the quickest restoration of
service possible and some customer amenities
will not be available until a permanent
terminal is constructed. All public access
areas and track zones will be open, though
weather protected. There will be no public
toilets, shops or eateries, but the terminal
will be fully ADA compliant and fully
accessible.
The completion of the temporary station and
resumption of PATH train service to the
World Trade Center site is the foundation of
restoring commuter and visitor access to
Downtown Manhattan even as planning proceeds
for a Lower Manhattan Transit Complex.
Envisioned as a combination of a new PATH
Terminal, the MTA's new Fulton Street
Transit Center, and pedestrian
connections linking these with the World
Financial Center and the WFC Ferry Terminal,
the Lower Manhattan Transit Complex is
slated for completion, in phases, over the
next three to six years.