Stage 2 for Ground Zero
|
| by Greg
Gittrich May 30, 2002 |
|
|
|
So much lies ahead.
This morning, the 16-acre plot the nation has come
to know as Ground Zero will formally close with the
ringing of a solitary bell and a mournful procession
out of the cavernous pit. Nearly nine months after a
pair of hijacked jets brought a storm of fire and
steel to lower Manhattan, the din of heavy
excavation machines will cease. And a quiet will
descend if only for a day. By tomorrow's
sunrise, laborers, machine operators, ironworkers,
carpenters, teamsters, cops and firefighters will
return.
Most will no longer work around the clock, but in
two 10-hour shifts. They will comb through the last
piles of debris in search of human remains. They
also must haul away about 25,000 tons of rubble and
finish securing the retaining wall that prevents the
Hudson River from rushing
in.
City officials acknowledge weeks will pass before
Ground Zero will be called clean, and say that work
could go well into July. Only then will progress be
measured strictly by rebuilding deadlines, rather
than bodies found and debris removed. "The
final ceremony is a very important milestone for the
recovery effort at Ground Zero," Gov. Pataki
said yesterday. "At the same time, we are going
to continue to move forward in a sensible way to
make sure that lower Manhattan comes back better
than it was on Sept. 10."
Viewing Wall Planned
When the cleanup ends, control of the site will
revert from the city to the Port Authority, which owns the land. Soon after, a
steel mesh viewing wall will be built around the
perimeter of the parcel, allowing the public to
watch as the rebuilding moves ahead. The list of
major projects already underway is staggering, but
also only a beginning.
As redevelopment honchos rush to meet a self-imposed
December deadline to determine what could rise above
ground, crews are rebuilding the underground.
Workers already have excavated the collapsed stretch
of the 1 and 9 subway lines and installed new steel
and concrete. The $1million-a-day project began in
March and is on track to be completed by late
October. Such a job would normally take three to
four years.
On the western edge of The
Pit, hardhats are ripping out the short-circuited
guts of the PATH system, which flooded after the
twin towers collapsed.
Sixty-five thousand commuters rode to the World
Trade Center station on the PATH trains each workday
before Sept. 11. Service is scheduled to resume in
2004 but at a bare-bones station. The
temporary depot will sit at the bottom of The Pit
and will be covered by a shed. A permanent hub
linking the PATH trains to 14 subway lines is
expected to open within five years. The tab is
expected to be about $2 billion.
Above ground, the damaged Winter Garden atrium is
scheduled to reopen
this year on Sept. 11. And to the north of the
main 16-acre parcel,
earthmoving machines like those that cleared paths
through the WTC
wreckage are busy preparing the site of a new 7
World Trade Center.
An architect hired by WTC leaseholder Larry
Silverstein envisions the new
tower as a light-emanating shaft with a concrete
core. The lower floors
will be used as a Con Ed substation.
Con Ed lost 10 transformer vaults when the original
7 WTC collapsed. It
needs the new substation online by the summer of
2003 to avoid power
shortages.
The foundation work for 7WTC will begin in a few
weeks. The office<
building could be completed as early as October 2005
likely years
before towers rise on the main parcel.
The agencies overseeing redevelopment, the Port
Authority and the
Lower Manhattan Development Corp. , last week
hired the architectural
firm Beyer Blinder Belle to help create a land use
plan for the site.
Up to six plans will be revealed in July and
narrowed to three in
September. A final plan will be selected in
December.
The plan will set aside land for a memorial. But the
actual memorial
design will be decided through a public process that
will be detailed in
July.
"There will be a transition from recovery to
construction," said Thomas
Wright, executive vice president of the Regional
Plan Association. "But for
the casual observer, there is going to be continuous
activity." |
| http://dailynews.yahoo.com/h/krnewyork/20020530/lo/stage_2_for_ground_zero_1.html |
|